Descaling Acidic Tank

General Information Of Sediment & Tank

General Information Of Sendiment

Diameter Tank 43 m
Height Sendimen 6.5 m
Volume Sendimen 9443.11

General Information Of Unit RL 08

Capacity Bucket 0.02
Time/Cycle 9 second

Estimation Cleaning Process

No of Cycle 472155 Cycle
Lead Time 4249398 Second
1180.39 Hour
49.1828 Day
No of Machine 2 Unit
Lead Time 24.5914 Day

General Procedure

1. New Manhole Fabrication & Rubber Lining
2. Digging, Loading, Hauling & Dumping Sediment with Excavator RL 08
3. Transfer sediment to outside tank with portable mini conveyor
4. Inspection after cleaning
5. Bottom rubber lining repair

Schedule Of Cleaning Process

Sludge Cutting Method

Cleaning Progress